BEND, Ore. - Here at ODOT, we are committed to providing a safe and efficient transportation system for everyone. We invest in Oregon's future through roadway improvement projects. The following projects are located within Region 4; Central Oregon from The Dalles to Klamath Falls on the east side of the Cascades.
There are two ways to learn about construction taking place for the upcoming week.
1. Visit TripCheck.com. Constantly updated with construction and crash data, TripCheck is the best way to learn about road conditions around the state. Click on a traffic cone symbol on the map to see construction impacts for that area.
2. Scroll down to the counties and highways listed below to see impacts that could affect you. Construction information is shown for one week, giving you the most up-to-date information.
All work is dependent on weather conditions, and schedules are subject to change.
DESCHUTES COUNTY
U.S. 97 NW Galloway Avenue - O'Neil Highway
Crews will be installing new striping throughout the project area Monday through Thursday nights between the hours of 7 p.m. and 7 a.m. The southbound and northbound fast lanes of U.S. 97 from mile point 117 to mile point 118 will be closed. Traffic will be controlled by flaggers. Expect minor delays.
Access to and from U.S. 97 to O’Neil Highway is closed. Please follow posted detours.
More project info here.
Expected completion - December 2026.
U.S. 97 & U.S. 20 Curb Ramps (Bend/Sisters)
BEND: Crews will be performing striping work along U.S. 20 at the intersections of Powers Road, Purcell Road, 27th Street, Butler Market, and Azure Drive. The work will occur Sunday through Friday from 8 p.m. to 6 a.m. with flaggers controlling traffic. Minor delays are expacted.
SISTERS: Crews will be performing nighttime striping work along U.S. 20 at the Pine Street intersection between the hours of 7 p.m. and 7 a.m. Traffic will be controlled by flaggers and drivers can expect minor delays.
More project information here
Expected completion- December 2026.
U.S. 97: Lower Bridge Way - Northwest 10th Street (Terrebonne)
Crews will be working throughout the project area placing landscape rock and installing signs with no impacts to traffic.
More project information here.
Expected completion- October 2026
Redmond/ Prineville ADA Ramps
Redmond: Crews will be performing striping work at 9th and 11th throughout the week. Drivers can expect nighttime lane closures from 7 p.m. to 7 a.m. with minimal traffic delays. During daytime hours, crews will be working throughout the project on minor punch list items with no impacts to traffic.
Prineville: Project complete.
More project information here.
Expected completion- September 2026
GILLIAM, SHERMAN & WASCO COUNTIES
U.S. 97 Moro - Grass Valley
Drivers should expect single lane closures controlled by flaggers Sunday night through Friday morning, 7 p.m. to 7 a.m. between mileposts 19 and 28. Delays up to 20 minutes are expected.
More project information here.
Expected completion- October 2026
JEFFERSON COUNTY
U.S. 97 Earl Street - Colfax Lane (Madras)
Crews will be working off the highway shoulder with no delays to traffic.
Plan Ahead: Work on the new storm sewer pipeline will begin this month on B Street. The street will remain open, with traffic shifted around the active work area. No significant traffic delays are expected. There will be no parking allowed in active work zones.
More project information here.
Expected completion- May 2028
KLAMATH COUNTY
OR 39: Merrill SRTS (Safe Routes to Schools) Project
Crews will be constructing new curb ramps and sidewalks as well as relocating the waterline. Traffic through the work zone will be managed by flaggers, expect delays up to 20 minutes.
More project information here.
Expected completion - October 2026
Questions or comments?
Meghan Blyth, community affairs coordinator
541-316-3941 or Meghan.L.Blyth@odot.oregon.gov