Paving of La Pine Area Roadways (La Pine Area) – Crews will be striping and doing shoulder work along 3rd Street, 5th Street, 6th Street, Pengra Road, Dorrance Meadow Road, and Walker Road.
Traffic Information – Road users should anticipate single-lane closures with flaggers and delays of up to 20 minutes during work hours. Works hours are expected to be 6 a.m. to 6 p.m., Monday through Friday.
Tumalo Reservoir Road Improvement (Bend Area) – Crews will be seeding the project area.
Traffic Information – Road users should expect lane closures with flaggers and delays of up to 20 minutes on Monday, Oct. 12, from 7 a.m. to 6 p.m.
Asphalt Paving and Repair (Sisters Areas) – Crews will be doing shoulder work on Pinehurst Road.
Traffic Information – Road users should anticipate single-lane closures with flaggers and delays of up to 20 minutes during work hours. Work hours are expected to be 7 a.m. to 5 p.m., Monday through Thursday.
Crack Sealing (Bend Area) – Crews will be crack sealing on Rickard Road.
Traffic Information – Road users should anticipate single-lane closures with flaggers and delays of up to 20 minutes during work hours. Work hours are expected to be 7a.m. to 5 p.m., Monday through Thursday.
Projects Administered by Other Agencies
Butler Market Road Utility Work – Crews will be installing underground utilities on Butler Market Road between Hamby Road and Hamehook Road.
Traffic Information – Road users should anticipate single-lane closures with flaggers and delays of up to 20 minutes.
Hamby Road and Ward Road Utility Work – Crews will be installing underground utilities on Hamby Road and Ward Road.
Traffic Information - Road users should anticipate single-lane closures with flaggers and delays of up to 20 minutes during work hours. Work hours are expected to be 7 a.m. to 5 p.m., Monday through Saturday.
La Pine Area Utility Work – Crews will be installing underground utilities on 1st Street, 4th Street, Bonnie Lane, Coach Road, Morson Street, and William Foss Road.
Traffic Information – Road users should anticipate single-lane closures with detours, single-lane closures with flaggers and delays of up to 20 minutes. Work hours are expected to be 7 a.m. to 5 p.m. Monday through Saturday.
Work adjacent to school property on Coach Road and 1st Street will be done on weekends.
U.S. 97: Terrebonne (Oregon Department of Transportation) – Crews will be landscaping and doing miscellaneous cleanup work along 11th Street, Smith Rock Way and adjacent roadways.
Traffic Information – Lower Bridge Way and Smith Rock Way are now open. Road users should use caution when navigating the new roundabout and roadway alignments.
For more information, visit the ODOT project website.
China Hat Road & FS Road 1815 Closure (US Forest Service) – China Hat Road and Forest Service Road 1815 are both closed at the USFS Boundary for forest restoration work.
Traffic Information – China Hat Road and FS Road 1815 are closed to all traffic at the end of County maintenance. Access to the area is closed until further notice.
*** Please note that work hours are subject to change based on weather conditions. ***