WEEKLY ROAD REPORT
October 26 - 30
Nels Anderson Road
Nels Anderson Road between Empire Avenue and N Highway 97 will have utility installations.
Northbound lane closure with detour, October 26 - December 18.
NW Bond Street
NW Bond Street between NW Colorado Avenue and NW Idaho Avenue for tree trimming work.
Single lane closure with lane shift, October 26 - 30 from 9 a.m. – 3:30 p.m.
NW Wall Street
NW Wall Street between NW Colorado Avenue and NW Arizona Avenue for service installations.
Single lane closure with lane shift, October 26 - 30 from 8:30 a.m. – 4 p.m.
NW Arizona Avenue
NW Arizona Avenue between NW Industrial Way and NW Staats Street for sewer and utility installations.
Single lane closure with lane shift, October 26 - 30 from 8:30 a.m. – 4 p.m.
NE Division Street
NE Division Street between Highway 20 and NW Lakeside Place will have NUID canal restoration.
Full closure with detour through April 5, 2027.
OB Riley Road
OB Riley Road between Crusher Avenue and Archie Briggs Road will have utility and paving work.
Single lane closure with flagging, October 29 - 30 from 8:30 a.m. – 4 p.m.
Archie Briggs Road
Archie Briggs Road between Crusher Avenue and OB Riley Road will have utility and paving work.
Single lane closure with flagging, October 29 - 30 from 8:30 a.m. – 4 p.m.
Pettigrew Road and Azalia Avenue Intersection
Intersection of Pettigrew Road and Azalia Avenue will have a sewer main installation.
Various single lane closures with flagging within the intersection through October 30 from 8:30 a.m. - 4 p.m.
NE Vail Lane
NE Vail Lane between NE 8th Street and NE 6th Street will have infrastructure installations related to a new subdivision.
Full road closure with local access through October 30 from 7 a.m. – 5 p.m.
Cooley Road and Ranch Village Drive
The City of Bend is constructing a new gravity sewer main along Cooley Road and Ranch Village Drive. This new line will connect to existing infrastructure west of the Cooley Road and 18th Street intersection, optimizing our community’s sewer system. Various road impacts will be required for the project including:
Cooley Road (Ranch Village Drive to the 18th Street/Cooley Road roundabout)
One lane will be closed, with two‑way traffic maintained through flagging through Fall 2026.
Construction activities on Cooley Road will be restricted during school drop-off and pick-up periods to minimize impacts to school traffic.
Restricted Hours:
• Morning drop-off: 7:30 a.m. - 9 a.m.
• Afternoon pick-up: 2 p.m. - 4 p.m.
• Early-release Wednesday pick-up: 12:30 p.m. - 2:30 p.m.
Ranch Village Drive (Double Peaks Drive to Cooley Road)
Closed to through traffic; local access only, through end of October.
Egypt Drive (Ranch Village Drive to 18th Street)
Closed to through traffic; local access only. Schedule: Estimated for the last week of October.
Franklin Avenue Improvements Project
Franklin Undercrossing Closure
Franklin Avenue undercrossing from Harriman Street to First Street is closed to vehicles until the end of May, temporarily reopening from Thanksgiving Day through New Year’s Day. This temporary closure will allow crews to continue construction of stormwater and transportation improvements, as well as new retaining walls at the undercrossing.
Detour routes include Third Street, Greenwood Avenue and Wall and Bond streets. Olney Avenue and Colorado Avenue will also be fully accessible during the undercrossing closure.
Bend Bikeway Project, SE Area
The Bend Bikeway Project provides safer connections for pedestrians and bicycles traveling between neighborhoods, schools, places of work, parks and trails across town. Improvements will include a new shared use path with work primarily occurring as shoulder work, with intermittent single lane closures and flagging.
Through Fall 2026. Streets affected:
• SE 9th Street between SE WIlson Avenue and SE Reed Market Road.
• SE 15th Street between the Larkspur park and Bronzewood Ave.
• NE Bear Creek Road between NE Alpenview Lane and SE Craven Road.
• NW Bond Street and NW Wall Street between NW Florida Avenue and NW Colorado Avenue, lane shift, October 21-23 from 8:30 a.m. – 4 p.m.
Windsor Drive
Windsor Drive between Brosterhous Road and Woodside Court for a sewer main installation (part of City Septic to Sewer Program).
Full road closure with local access only through mid-November.
King Hezekiah and Fargo Sewer Project
Various Road closures will be required for the installation of new sewer mains. Road closures listed below:
• SE King Hezekiah Way between SE 15th Street and King Jehu through mid-November.
Highway 20
ODOT ADA Ramp Installations – Various ADA ramps along Highway 20 will be replaced during overnight work from 8 p.m. – 6 a.m. with minimal delays.
Work to occur through October 2026.
Intersections affected:
• Powers Road
• Butler Market Road
• Purcell Boulevard
• 27th Street
Upcoming Roadway Impacts:
Veterans Day Parade (special event)
Various road closures in and around downtown (listed below) on Wednesday, November 11.
• NW Wall Street between NW Newport Avenue and NW Franklin Ave
• NW Riverside Boulevard between NW Wall Street and NW Galveston Avenue
• NW Galveston Avenue between NW Tumalo Avenue and NW Harmon Boulevard
• NW Harmon Boulevard between NW Galveston Avenue and NW Newport Avenue
• NW Newport Avenue between NW Harmon Boulevard and NW Wall Street
Work schedules are dependent on weather conditions and other factors. Always exercise increased caution within construction zones. Drivers should use designated detour routes. Nearby residential streets are for local traffic only.
Any road closure not listed within this report, please submit a service request to notify the City of any potentially unpermitted work within City right-of-way.
Contact Information
Alex Pelayo, Project Engineer 541-323-8556, apelayo@bendoregon.gov
For Street Preservation related questions:
Paul Neiswonger, Streets Supervisor 541-317-3035, pneiswonger@bendoregon.gov
Closures and detours in Bend are updated weekly: